In the Project dialog, the % Complete field shows a calculated percentage of budgeted hours for all completed tasks relative to the total budgeted hours for the project.

Example Example:

Task Budgeted Hours Tracking
Task 1 5.0 Completed
Task 2 2.0 Completed
Task 3 3.0 Not Started
Project Total Budgeted Hours 10.0

% Complete: (5.0 + 2.0) / 10 = 0.70, or 70%