Practice CS: Unable to change a task to not completed

Show expandable text

When you complete a project, all the tasks are automatically completed. If you need to change the status of a task to something other than completed, you'll need to update the status of the project to not completed as well. 

  1. Open the project by double-clicking on the project or clicking the Edit button, if available.
  2. Click the Tasks tab.
  3. Open the task whose Tracking Description you want to change by double-clicking on it or clicking the Edit button, if available.
  4. Change the Tracking Description on the task.
  5. Click OK.
  6. Click the Main tab.
  7. Change the Tracking Description to anything other than Completed.
  8. Click OK.

Was this article helpful?

Thank you for the feedback!